Construction of the Ambarlı Advanced Biological Wastewater Treatment Plant
Discover our high-impact domestic and international projects, driving excellence across wastewater treatment, public infrastructure, industrial facilities, and cutting-edge energy systems—categorized for your exploration.

Client: Istanbul Water and Sewerage Administration (İSKİ) Main Contractor: Alke-PWT-Faber Consortium
01.02.2008 - 30.06.2012
Scope: Engineering, Procurement, Construction, Commissioning
Process: Advanced Biological Wastewater Treatment (N-P Removal)
Units: Wastewater lift stations, sand-grease removal unit, screening building, primary sedimentation tanks (2xØ49 m), bio-P tanks (34.195 m3), aeration tanks (272.800 m3), secondary clarifier tanks (2xØ51.80 m), pump stations, water tanks, blower building, sludge thickening-dewatering-thermal sludge drying building, sludge digestion tanks, excess sludge storage tanks, dry gas tanks, cogeneration unit (2 units x 4.6 MW), biofilter control unit, ozone odor control unit, wastewater recovery and ultrafiltration unit.