Kemer-Çamyuva Wastewater Treatment Plant and Associated Infrastructure Facilities Construction Project

Atıksu arıtma, kamu binaları, endüstriyel tesisler ve enerji altyapısı alanlarında yurt içi ve uluslararası projelerimizi kategoriye göre inceleyebilirsiniz.

Ministry of Culture and Tourism, Directorate General of Investments and Enterprises

27.01.2023 – 27.03.2024

Scope: Supply, Equipment Procurement and Installation, Construction, Commissioning

Process: Turnkey Construction Works

Units: Influent Flow Meter Structure, Fine Screen Structure, Grit and Grease Trap, Perforated Screen Structure, Bio-P Basin, Aeration Basin, Final Settling Basin, Disinfection Unit, Effluent Flow Meter Structure, Sludge Storage Basin, Sludge Dewatering Building, Blower Building, Odour Control Unit, administrative and ancillary facilities, and 2 pumping stations