Kemer-Çamyuva Wastewater Treatment Plant and Associated Infrastructure Facilities Construction Project
Atıksu arıtma, kamu binaları, endüstriyel tesisler ve enerji altyapısı alanlarında yurt içi ve uluslararası projelerimizi kategoriye göre inceleyebilirsiniz.

Ministry of Culture and Tourism, Directorate General of Investments and Enterprises
27.03.2024 - 27.03.2034
Scope: Operation of the wastewater treatment plant for 10 years
Process: Turnkey Construction Work
Units: Inlet Flow Meter Structure, Fine Screen Structure, Grit and Grease Trap, Perforated Screen Structure, Bio-P Basin, Aeration Basin, Final Settling Basin, Disinfection Unit, Outlet Flow Meter Structure, Sludge Storage Basin, Sludge Dewatering Building, Blower Building, Odor Control Unit, administrative and auxiliary facilities, and 2 pumping stations