TS-CW-01: Rehabilitation of Wastewater Treatment Plants (Design, Supply and Installation) / Lot 1: Rehabilitation of the 60,000 m³/day wastewater treatment plant in Bekabad City, UZBEKISTAN

Atıksu arıtma, kamu binaları, endüstriyel tesisler ve enerji altyapısı alanlarında yurt içi ve uluslararası projelerimizi kategoriye göre inceleyebilirsiniz.

“Uzsuvtaminot” Joint Stock Company

27.08.2022 – Ongoing

Scope: Engineering, Procurement, Equipment Supply and Installation, Construction, Commissioning

Process: Biological Treatment (C-N Removal)

Units: Screening Unit, Sand and Oil Removal Unit, Aeration Tank, Final Settling Tank, Biological Ponds, Chlorine Contact Tank, Gravity Thickening, Aerobic Stabilization Tank, Sludge Drying Beds