Bodrum Turgutreis WWTP 1st Stage (37,000 m3/day) and Sea Discharge Construction
İşveren
Muğla General Directorate of Water and Sewerage Administration (MUSKI)
Tarih
13.01.2021– 31.10.2023
Tesis Kapasitesi
37.000 m3/gün
Açıklama
EMPLOYER
Mugla Water and Sewerage Administration
General Directorate (MUSKI)
HISTORY
13.01.2021- 31.10.2023
FACILITY CAPACITY
37.000 m3/day
EXPLANATION
Scope: Application Design, Equipment Supply and Installation, Construction, Commissioning Works
Process: Advanced Biological Wastewater Treatment (N-P Removal)
Units: Inlet pump station, physical treatment plants, Anaerobic BioP ponds, activated sludge tanks, final settling tanks, RAS&WAS pump station, sludge treatment plants (sludge equalization tank and dewatering unit), mechanical filters, UV disinfection unit, deodorization unit, sea discharge and all necessary auxiliaries.
Projects
Explore More
We will provide an overview of our ongoing construction projects, including timelines and milestones.
Ertürk Sok. NO:1 K1 Plaza Beykoz - İstanbul
+90 216 693 23 14
+90 216 693 23 18
Homepage
Projects
About Us
Sustainability
Career
© ALKATAŞ İNŞAAT VE TAAHHÜT A.Ş