Samsun East Advanced Biological Wastewater Treatment Plant and Deep Sea Discharge Design-Build Project
İşveren
Samsun Water and Sewerage Administration (SASKI)
Tarih
10.10.2011 / 01.09.2014
Tesis Kapasitesi
WWTP : 105,000 m3/day Sea Discharge : 120.000 m3/day
Açıklama
Scope: Engineering, Procurement, Construction, Commissioning, Commissioning, 5-Year Operation according to FIDIC Design, Build and Operate Contract Conditions
Process: Advanced Biological Wastewater Treatment (N-P Removal)
Units: Two inlet pumping stations, physical treatment plants, BioP ponds, advanced biological wastewater treatment plant, sludge treatment units, deodorization units, wastewater pumping station, deep sea discharge and administrative and auxiliary buildings.
Projects
Explore More
We will provide an overview of our ongoing construction projects, including timelines and milestones.
Treatment and Infrastructure
Business
Energy Facilities
Superstructure Construction
Ertürk Sok. NO:1 K1 Plaza Beykoz - İstanbul
+90 216 693 23 14
+90 216 693 23 18
© ALKATAŞ İNŞAAT VE TAAHHÜT A.Ş